Where Sadler Road meets South Fletcher Avenue, a boardwalk complex built around 2004 still carries people from the parking lot to the sand. The lot is part asphalt, part crushed shell. Beside it, the beach approach next to Sliders Seaside Grill wears away often enough that city staff named it as one of the recurring maintenance problems at the site. In the City's own description of the site, the area "has experienced little to no structural development changes over the past several decades."
That changes soon, and the timing matters beyond this one beach. Seaside Park is the first of seven public beach parks on Amelia Island to be rebuilt under a joint city-county plan. It keeps its shape, its parking capacity and its neighbor at 1998 South Fletcher Avenue. Everything a visitor touches between the car and the dune walkover gets replaced, built to a shared design the other six parks are meant to follow.
A park chosen because it was wearing out
The program is called the Amelia Island Beach Harmonization. Its seven sites are North Beach, Main Beach, Seaside Park, Peters Point, Burney Park, the Scott Road Access Point and the Southend Beach Access. The planning and design firm EDSA produced the final conceptual plan, dated September 12, 2022. It sets common rules for every site: consistent signage, a shared architectural character, matching hardscape and furnishings, dune protection, native planting, shade, and parking capacity held where it applies, with pervious surfaces favored.
Seaside went first because of its condition. According to the Fernandina Observer's April report, the presentation to commissioners said the park was chosen for its aging infrastructure and deteriorating conditions. The same report said public outreach drew more than 1,200 survey responses, 86% of them from Fernandina Beach residents. At a March 10, 2026 meeting of the Parks and Recreation Advisory Committee, staff said the boardwalk complex dated to about 2004 and was "nearing the end of its life." Staff said the City had committed about two years earlier to replacing one section, on the understanding that the rest would follow.
Deputy City Manager Jeremiah Glisson described the program's scope to commissioners in April, as the Observer reported:
"It's less of a single project and more of a master plan framework guiding decisions over decades."
That framework means the choices made at Sadler Road carry well past this one park. The signage, pavilions, materials and furnishings installed here are meant to set the pattern the island's other beach parks will share.
Same footprint, new pieces
People who already use Seaside will find their routine mostly where it was. Max Spann of Halff Associates, the design and engineering firm, told commissioners there was "not much that we can actually change as far as the organization of items… we can do improvements to the original layout," the Observer reported. The parking is reworked without reducing total spaces, and the plan adds bike parking, shared-use paths, wayfinding signs and marked pedestrian crossings.
The City's bid document, ITB 27-02, lists what gets removed and what goes in.
Element | Coming out | Going in |
|---|---|---|
Pavilions | Six, about 2,432 sq ft total | Six, about 2,169 sq ft total |
Boardwalk | About 1,458 sq ft | About 208 linear ft at 6 ft wide |
Parking surface | About 24,842 sq ft of asphalt and crushed shell | About 11,380 sq ft concrete drive aisle and 9,967 sq ft of pavers |
Rinse-off | None listed | Two outdoor showers |
Signs | Existing signage removed | One monument sign plus identity, information, education and regulatory signs |
Planting | Existing landscaping removed | New landscaping with automatic irrigation |
The pavilion count stays at six while their combined footprint shrinks by roughly a tenth. The new boardwalk works out to about 1,248 square feet. The paved area drops by about 3,500 square feet with no loss of spaces, and about 783 square feet of sand-filled geocell grid goes in for stabilization.
At the March meeting, staff explained the paving. The lot gets a concrete drive aisle with pavers on either side, which lets stormwater drain while being "a little more maintenance-friendly than what's there." The eroding approach at Sliders gets what staff called a concrete drive aisle extension. Below ground, the bid calls for a dry retention area, about 749 linear feet of 24-inch exfiltration trench and about ten concrete drainage structures. In the Observer's account, the drainage moves from surface ponding to underground systems.
The dune walkover is the one piece left mostly in place. It was rebuilt within the past few years, so the bid treats its replacement as an add-on option. Under that option, about 285 linear feet of wooden decking from the beach to the new section would be swapped for composite decking to match the rest of the project.
What the design protects
Some changes are meant to limit how far people go. The plan uses turtle-friendly lighting, keeps planting out of the low interior areas where most of the wildlife is, and leaves a buffer to keep visitors from walking down into them. Asked whether foot traffic into the park's protected interior would be allowed, Spann answered plainly: "We're discouraging it," as the Observer reported.
The on-beach parking area at Seaside is managed the same way. When the Army Corps of Engineers tilled the beach from Main Beach to Seaside this spring after the renourishment project, the City asked the crews to stay out of the Seaside on-beach parking area. Staff said they did not want to encourage turtles to nest there or leave vehicles stuck in loosened sand. The rebuild applies the same reasoning to the permanent design: cars stay on firm, defined surfaces and the dunes are left alone.
The money and the calendar
The project was estimated at $3.9 million in April. The funding plan pairs a 30% city share with 70% from Nassau County tourist development tax revenue. When the City Commission approved the conceptual framework in 2023, it required the City to oversee design and construction of improvements at its own beach parks before county money is spent. On August 18, 2026, the City approved the interlocal agreement with Nassau County. It covers the island-wide program, with Seaside as the first project and the City managing bidding and construction, according to Citizen Portal's summary of the meeting.
The April forecast of construction this fall has given way to the bid calendar. The project is still in procurement, and the City's bid listing sets the remaining dates:
- November 17, 2026: final addendum issued to bidders.
- November 30, 2026, 2 p.m.: deadline for bids.
- After award: the City issues a notice to proceed, and the contractor must begin work within seven days.
- 90 days after the notice: substantial completion.
- 120 days after the notice: final completion.
In March, staff called finishing before the next beach season "ideal" and said the schedule depended on settling the City's share of the costs. The funding agreement has since been approved, so the 120-day contract window now sets the pace.
After Sadler Road
Main Beach is on the list, and staff said in March that the City has seen concepts for it. Asked whether it might come within about five years, staff declined to commit to a schedule until Seaside's construction schedule and probable costs were in hand. Peters Point and Scott Road were named among the others, and staff said "all seven parks are getting a facelift," according to the recording of the March 10 meeting.
The pavilions, signs, boardwalk and paving installed at the foot of Sadler Road over the coming months are the first full version of a design meant to repeat from North Beach to the Southend Beach Access. Anyone curious about how Main Beach or Peters Point might look in later phases can watch it go in here.
On the island's west shore, at The Landings on Amelia River, the morning starts with the marsh and the Intracoastal from a terrace of roughly 600 square feet. Sadler Road leads to the other side of the island and the Atlantic. If you would like to see both shores in a single day, we would be glad to show you the river side. Schedule a Private Tour.